In reply to Mr BASHAM (Finniss) (25 June 2025). (Estimates Committee A)
The Hon. N.D. CHAMPION (Taylor—Minister for Housing and Urban Development, Minister for Housing Infrastructure, Minister for Planning): I have been advised:
In delivering the capital program, SA Water work on a number of large, complex and strategically important projects at various stages across the project lifecycle.
The major projects that comprise the $46 million that SA Water will progress during the 2025-26 financial year are included in the table below.
Project Name | 2025-26 State Budget Outcome $000's |
Main South Rd Duplication Stage 2 | 101 |
Myponga UV Treatment | 306 |
Millicent Wastewater Treatment Plant Upgrade | 653 |
Fleurieu Water Quality Improvement | 864 |
Port Augusta East Wastewater Treatment Plant Upgrade | 930 |
NAIS Infrastructure | 1,100 |
Bolivar WWTP Capacity Growth Upgrade | 1,165 |
Leigh Creek Brine Transfer Pipeline/Lagoon Upgrade | 1,317 |
Baroota Dam Safety (Investigation) | 1,341 |
Wirrina Cove Pipe, Pump Station & Tank | 3,101 |
KI Desalination Plant | 3,625 |
Bordertown—New tank arrangements | 6,036 |
Mount Bold Dam Safety Investigation | 7,496 |
Gawler EL118 1.27ML Storage Tank | 9,413 |
Non-Regulated Major Projects | |
Mt Barker Water Supply Investigation—Stage 1 | 6,300 |
Third Party Works- Main South Rd Duplication Stage 2 | 516 |
Zero Cost Energy Future | 1,956 |
'Major Projects' Total | 46,219 |