House of Assembly - Fifty-Second Parliament, Second Session (52-2)
2012-05-01 Daily Xml

Contents

STATUTES AMENDMENT (NATIONAL ENERGY RETAIL LAW IMPLEMENTATION) BILL

Final Stages

The Legislative Council agreed to the bill with the amendments indicated by the following schedule, to which amendments the Legislative Council desires the concurrence of the House of Assembly:

No. 1. New clause, page 6, after line 22—Insert:

13A—Amendment of section 36AC—Interpretation

Section 36AC—after its present contents (now to be designated as subsection (1)) insert:

(2) For the purposes of the definition of excluded generator, if there are 2 or more meters for measuring the consumption of electricity on a site owned or occupied by 1 customer, in assessing the purpose of the installation of a generator on the site to determine whether or not the generator is an excluded generator, the operator of the distribution network must take into account the electricity consumption of the customer on the site as a whole (despite the fact that, for example, most or all of the electricity consumption on the site is recorded by a different meter from the meter to which the generator is connected).

No. 2. New clause, page 6, before line 23—Insert:

13B—Amendment of section 36AE—Feeding electricity into networks—requirements on holder of licence authorising operation of distribution network

Section 36AE(6)(a)—after 'electricity' insert:

, unless the alteration was approved before 1 October 2011 by the holder of the licence authorising the operation of a distribution network to which the generator is connected