ERNABELLA ANANGU SCHOOL

209 Dr McFETRIDGE (Morphett) (21 October 2008). With respect to the contract DTEI-BM21 for the Ernabella Anangu school redevelopment:

(a) has this project been completed and if so;

(b) was it completed on time;

(c) was it completed within budget;

(d) who was the successful contractor; and

(e) who 'signed off' on the completed project?

The Hon. J.W. WEATHERILL (Cheltenham—Minister for Environment and Conservation, Minister for Early Childhood Development, Minister for Aboriginal Affairs and Reconciliation, Minister Assisting the Premier in Cabinet Business and Public Sector Management): The Minister for Education has provided the following information:

(a) The new Child Parent Centre for Ernabella Anangu School has been completed.

(b) The building contractor experienced some resourcing and inclement weather issues causing some delay to the completion of the CPC.

(c) Final costs are determined at the end of the defects liability period (i.e. 12 months after project completion).

(d) Murray River North Pty ltd was the successful contractor.

(e) The project architect 'signed off' on the completed project.