APY LANDS SUBSTANCE MISUSE FACILITY

208 Dr McFETRIDGE (Morphett) (21 October 2008). With respect to the contract DTEI-BM20 for the Anangu Pitjantjara Yankunytjatjara lands substance misuse facility:

(a) has this project been completed and, if so;

(b) was it completed on time;

(c) was it completed within budget;

(d) who was the successful contractor; and

(e) who 'signed off' on the completed project?

The Hon. J.W. WEATHERILL (Cheltenham—Minister for Environment and Conservation, Minister for Early Childhood Development, Minister for Aboriginal Affairs and Reconciliation, Minister Assisting the Premier in Cabinet Business and Public Sector Management): The number quoted by the honourable member is a Department of Transport Energy and Infrastructure (DTEI) reference number (not contract number) for a contract to build staff housing associated with the APY Lands Substance Misuse Facility in Amata.

Yes, the project has been completed.

No. The contract was due for completion on 29 August 2007. Actual completion was 30 November 2007.

Yes, the project was completed within budget.

The contract was with Chapman Building Industries.

All practical completion certificates are issued by DTEI Building Management.