House of Assembly - Fifty-Fourth Parliament, Second Session (54-2)
2021-02-03 Daily Xml

Contents

School Infrastructure Projects

In reply to Mr BOYER (Wright) (23 November 2020). (Estimates Committee B)

The Hon. J.A.W. GARDNER (Morialta—Minister for Education): I am advised of the following:

The context for this question is the capital works program and round 1 and 2 projects that may be progressing past the December 2021 target date with some non-classroom related works which will continue into 2022.

At this stage there is only one project that falls in this category as reported by the Department for Infrastructure and Transport which is Norwood Morialta High School.

Currently all other round 1 and 2 projects are scheduled for completion before or by December 2021.