House of Assembly: Thursday, September 12, 2019

Contents

North-South Corridor

In reply to the Hon. A. KOUTSANTONIS (West Torrens) (30 July 2019). (Estimates Committee A)

The Hon. S.K. KNOLL (Schubert—Minister for Transport, Infrastructure and Local Government, Minister for Planning): I have been advised by the Department of Planning, Transport and Infrastructure—

There are currently approximately 56 FTEs working on the existing north-south corridor projects including the Darlington upgrade, Pym to Regency, Torrens to Torrens and the Northern Connector.

This includes FTEs that work specifically on the north-south corridor projects which are both directly and indirectly charged to the project.

Note that this excludes corporate support staff that are indirectly supporting the delivery of these projects. Also note that this FTE figure may change dependent on the stages of the works from year to year.