House of Assembly: Tuesday, October 16, 2018

Contents

Road Upgrades

In reply to the Hon. A. PICCOLO (Light) (4 September 2018).

The Hon. S.K. KNOLL (Schubert—Minister for Transport, Infrastructure and Local Government, Minister for Planning): I have been advised of the following:

Early service relocation works commenced on Monday 27 August 2018 and are currently in progress. The main intersection upgrade works are scheduled to commence in October 2018 with the project currently expected to be completed in February 2019.