MARINE MAINTENANCE

420 Dr McFETRIDGE (Morphett) (8 April 2008). For each operating and marine maintenance project that will be completed in 2007-08, how much has been allocated to each project and what is the timeframe for its completion?

The Hon. P.F. CONLON (Elder—Minister for Transport, Minister for Infrastructure, Minister for Energy): I provide the following information:

Operating marine projects anticipated to be completed in 2007-008:

Project Cost Completion Date
General fixed costs such as utilities, insurances, property management, staff salaries, Port Bonython shipping management fees, oil waste station fixed costs and various other fees and charges $2.2 million ongoing


Marine maintenance projects anticipated to be completed in 2007-008:

Project Cost Completion Date
Routine maintenance of aids to navigation $400 000 ongoing
Hydrographic survey of Port Bonython channel and inspection of navigation beacons $56 000 May 2008
Quick release mooring hooks refurbishment at Port Bonython $120 000 September 2007
July 2007 storm damage excess to several jetties and Penneshaw breakwater $100 000 April 2008
Beachport boatyard, maintenance work on straddle carrier $70 000 May 2008
General routine jetty maintenance $120 000 ongoing
Supply of 150 box piles for reserve stock $350 000 December 2007
North Haven dredging works $380 000 October 2007
Tide gauges maintenance program $40 000 ongoing
Venus Bay abutment works $80 000 June 2008
Largs Bay jetty refurbishment $470 000 April 2008
Wardang Island jetty demolition $380 000 September 2007
Coffin Bay jetty re-decking $60 000 June 2008