MARINE MAINTENANCE
420 Dr McFETRIDGE (Morphett) (8 April 2008). For each operating and marine maintenance project that will be completed in 2007-08, how much has been allocated to each project and what is the timeframe for its completion?
The Hon. P.F. CONLON (Elder—Minister for Transport, Minister for Infrastructure, Minister for Energy): I provide the following information:
Operating marine projects anticipated to be completed in 2007-008:
| Project | Cost | Completion Date | 
| General fixed costs such as utilities, insurances, property management, staff salaries, Port Bonython shipping management fees, oil waste station fixed costs and various other fees and charges | $2.2 million | ongoing | 
Marine maintenance projects anticipated to be completed in 2007-008:
| Project | Cost | Completion Date | 
| Routine maintenance of aids to navigation | $400 000 | ongoing | 
| Hydrographic survey of Port Bonython channel and inspection of navigation beacons | $56 000 | May 2008 | 
| Quick release mooring hooks refurbishment at Port Bonython | $120 000 | September 2007 | 
| July 2007 storm damage excess to several jetties and Penneshaw breakwater | $100 000 | April 2008 | 
| Beachport boatyard, maintenance work on straddle carrier | $70 000 | May 2008 | 
| General routine jetty maintenance | $120 000 | ongoing | 
| Supply of 150 box piles for reserve stock | $350 000 | December 2007 | 
| North Haven dredging works | $380 000 | October 2007 | 
| Tide gauges maintenance program | $40 000 | ongoing | 
| Venus Bay abutment works | $80 000 | June 2008 | 
| Largs Bay jetty refurbishment | $470 000 | April 2008 | 
| Wardang Island jetty demolition | $380 000 | September 2007 | 
| Coffin Bay jetty re-decking | $60 000 | June 2008 | 