MARINE MAINTENANCE
420 Dr McFETRIDGE (Morphett) (8 April 2008). For each operating and marine maintenance project that will be completed in 2007-08, how much has been allocated to each project and what is the timeframe for its completion?
The Hon. P.F. CONLON (Elder—Minister for Transport, Minister for Infrastructure, Minister for Energy): I provide the following information:
Operating marine projects anticipated to be completed in 2007-008:
Project | Cost | Completion Date |
General fixed costs such as utilities, insurances, property management, staff salaries, Port Bonython shipping management fees, oil waste station fixed costs and various other fees and charges | $2.2 million | ongoing |
Marine maintenance projects anticipated to be completed in 2007-008:
Project | Cost | Completion Date |
Routine maintenance of aids to navigation | $400 000 | ongoing |
Hydrographic survey of Port Bonython channel and inspection of navigation beacons | $56 000 | May 2008 |
Quick release mooring hooks refurbishment at Port Bonython | $120 000 | September 2007 |
July 2007 storm damage excess to several jetties and Penneshaw breakwater | $100 000 | April 2008 |
Beachport boatyard, maintenance work on straddle carrier | $70 000 | May 2008 |
General routine jetty maintenance | $120 000 | ongoing |
Supply of 150 box piles for reserve stock | $350 000 | December 2007 |
North Haven dredging works | $380 000 | October 2007 |
Tide gauges maintenance program | $40 000 | ongoing |
Venus Bay abutment works | $80 000 | June 2008 |
Largs Bay jetty refurbishment | $470 000 | April 2008 |
Wardang Island jetty demolition | $380 000 | September 2007 |
Coffin Bay jetty re-decking | $60 000 | June 2008 |