In reply to the Hon. J.A.W. GARDNER (Morialta—Deputy Leader of the Opposition) (26 June 2024). (Estimates Committee A)
The Hon. B.I. BOYER (Wright—Minister for Education, Training and Skills): I have been advised that for the Department for Education:
The estimated total cost for the engagement of consultants in 2024-25 is $2million as outlined in the 2024-25 Agency Statements Volume 1 page 187. Decisions about the engagement of consultants are made on a case by case basis.
The following new contracts (excluding contracts that may have variations) have been executed by the department since 1 July 2024 per information recorded in the department's central procurement system.
Contractor Name | Method of Appointment | Reason for the engagement | Total estimated cost |
ASI SOLUTIONS | Limited, request for quote | Procurement of a portal to enable the purchase of devices to support the Digital Strategy. | There is no commitment to purchase devices. |
KERRY BURKE | Limited, request for quote | Engagement of Psychology Providers | $70K for 24-25 year only |
GEMMA HEPBURN | Limited, request for quote | Engagement of Psychology Providers | $65K for 24-25 year only |
THE TRUSTEE FOR TEK CO TRUST | Limited, request for quote | Onsite weekly servicing and maintenance support arrangement of Orbis' audio visual environment. | $357K over 3 years commencing July 24 |
The department's central procurement system does not maintain contract information where the total contract value is less than $55,000, so details on any contractors below $55,000 are not included in this response.
The department will outline all names of the contracting firms and the work undertaken above $10,000 that were engaged in 2024-25 as part of the department's 2024-25 annual report once it is finalised and audited.