North-South Corridor
In reply to the Hon. A. KOUTSANTONIS (West Torrens) (3 August 2021). (Estimates Committee A)
The Hon. C.L. WINGARD (Gibson—Minister for Infrastructure and Transport, Minister for Recreation, Sport and Racing): I have been advised:
The breakdown of the estimated result of $41.5 million is provided. Note that the actual expenditure for 2020-21 is subject to finalisation of audited financial statements.
$17.4 million – Planning works and program management, including final business case, traffic modelling, planning studies and staffing resources.
$12.2 million – Engineering and design, including the reference design.
$7.5 million – Early and enabling works, including ground investigations, engineering surveys and utility relocation works.
$4.4 million – Land acquisitions and associated costs.