Contents
-
Commencement
-
Parliamentary Procedure
-
-
Parliamentary Committees
-
-
Bills
-
-
Personal Explanation
-
-
Bills
-
-
Petitions
-
Parliamentary Procedure
-
Ministerial Statement
-
-
Parliamentary Committees
-
-
Question Time
-
-
Grievance Debate
-
-
Parliamentary Procedure
-
-
Bills
-
-
Parliamentary Committees
-
Estimates Replies
-
Carryover Expenditure
In reply to the Hon. A. KOUTSANTONIS (West Torrens) (30 July 2021). (Estimates Committee A)
The Hon. D.C. VAN HOLST PELLEKAAN (Stuart—Minister for Energy and Mining): I have been advised the following:
For the Department for Energy and Mining, the budgeted expenditure on goods and services for the financial year 2021-20 and each of the years of the forward estimates period is as follows:
21/22 | 22/23 | 23/24 | 24/25 | 25/26 | |
$'000 | $'000 | $'000 | $'000 | $'000 | |
Total goods and services | 42,436 | 31,548 | 30,371 | 28,475 | TBA |
The top 10 providers of goods and services for the financial year 2020-21 and the cost for these goods and services were as follows:
Supplier | Total Value (excl. GST) |
SA Power Networks | $9,280,623 |
Cowell Electric Supply | $5,685,870 |
Mogas Regional Pty Ltd | $5,237,957 |
Hornsdale Power Reserve P/L | $3,927,943 |
Electranet Pty Ltd | $3,600,000 |
Department for Infrastructure and Transport (DIT) | $3,245,552 |
Department of Primary Industries and Regions (PIRSA) | $1,783,283 |
Department for Innovation and Skills | $1,464,070 |
KPMG | $1,286,904 |
Money Mob Talkabout Ltd | $950,029 |
The top ten providers of goods and services for the financial year 2020-21 and the description of these goods and services is as follows:
Supplier | Description |
SA Power Networks | Operation costs for the state's temporary generators. |
Cowell Electric Supply | Electricity generation, distribution and retail services for the Remote Area Energy Supply scheme. |
Mogas Regional Pty Ltd | Fuel for the Remote Area Energy Supply scheme. |
Hornsdale Power Reserve P/L | Operation of the Hornsdale Power Reserve. |
Electranet Pty Ltd | Interconnector Underwriting Agreement. |
Department for Infrastructure and Transport (DIT) | Office accommodation expenses. |
Department of Primary Industries and Regions (PIRSA) | Information Communication Technology services provided under service level agreement. |
Department for Innovation and Skills | Corporate services support provided under service level agreement. |
KPMG | Hydrogen Export Study, Modelling Tool and Prospectus. |
Money Mob Talkabout Ltd | Provision of education services for the introduction of smart meter education, electricity payment and introduction to energy efficiency in 2020-2021. |