Contents
-
Commencement
-
Bills
-
-
Parliamentary Procedure
-
Ministerial Statement
-
-
Question Time
-
-
Parliamentary Procedure
-
Question Time
-
-
Grievance Debate
-
-
Parliamentary Committees
-
-
Bills
-
-
Answers to Questions
-
-
Estimates Replies
-
Salisbury East High School
In reply to Mr GARDNER (Morialta) (4 August 2016).
The Hon. S.E. CLOSE (Port Adelaide—Minister for Education and Child Development, Minister for Higher Education and Skills): I have been advised:
Prior to the 2015-16 financial year, completed projects were reported on a separate line. From 2015-16 onwards, projects that have reached practical completion and have no current year budget or expected expenditure are generally included against Small Projects. The redevelopment of Salisbury East High School was complete and had no 2016-17 budget or expected expenditure and therefore fit that category. This is why it was not listed on that table.
The Trade Training Centres had no budget for 2016-17, however all projects had not yet reached practical completion (Warriappendi was completed on 21 July 2016). Therefore it continued to be listed separately as an existing project.
Construction at Salisbury East High School was completed in September 2015.
The final expenditure for the project was $7.78m which included additional works requested and funded by the school.