Legislative Council: Tuesday, September 18, 2012

Contents

OPAL FUEL

In reply to the Hon. T.J. STEPHENS (15 May 2012).

The Hon. I.K. HUNTER (Minister for Communities and Social Inclusion, Minister for Social Housing, Minister for Disabilities, Minister for Youth, Minister for Volunteers): The Minister for Aboriginal Affairs and Reconciliation has been advised:

1. A number of issues have significantly delayed the availability of Opal fuel at Yalata including a change in the preferred location for the fuel tanks and complex tenure and regulatory issues associated with the site.

2. Delays have occurred while the complexities are being addressed.

3. Commonwealth funds are not being held by any stakeholder.

4. A fully operational Opal fuel outlet for Yalata will be installed when the required plans, approvals and costings have been finalised. It is anticipated that it will take 3 to 4 months to complete installation once a new Commonwealth funding contract is in place, which is expected to happen in the near future.