In reply to Mr PATTERSON (Morphett) (1 November 2023).
The Hon. S.E. CLOSE (Port Adelaide—Deputy Premier, Minister for Industry, Innovation and Science, Minister for Defence and Space Industries, Minister for Climate, Environment and Water): I have been advised:
Below a breakdown programs/projects and changes in expenditure and milestone profiles:
Project | Original Budget ($) | Actual ($) | Variance ($) | Comment |
Defence Jobs Attraction Campaign | - | 177,385 | (177,385) | Timing of grant programs and provision of scholarships delayed expenditure, funding carried over from 2021-22 in revised 2022-23 Budget. |
SASAT-1 ( Kanyini) | 474,000 | 1,477,100 | (1,003,100) | Budget carried over from 2021-22 to fund project, in revised 2022-23 Budget. |
Submarine Task Force | 300,412 | 556,950 | (256,538) | Funding carried over from 2021-22 in revised 2022-23 Budget. |
DSA Operations | 2,501,588 | 2,506,565 | (4,977) | Minor movements |
Total | 3,276,000 | 4,718,000 | (1,442,000) |
Kanyni is currently planned for a mid-2024 launch into low Earth orbit.