House of Assembly: Thursday, June 10, 2021

Contents

Answers to Questions

Country Health Services

454 Mr PICTON (Kaurna) (5 May 2021). For each individual country health stimulus project as part of the COVID-19 stimulus package:

(a) What is the current status of each project as of 4 May 2021?

(b) What is the amount spent on each project as of 4 May 2021?

(c) What is the expected completion date of each project as of 4 May 2021?

(d) How much remains to be spent on each project as of 4 May 2021?

(e) How many employees have been hired for each project as of 4 May 2021?

The Hon. J.A.W. GARDNER (Morialta—Minister for Education): The Minister for Health and Wellbeing has been advised:

The status of the initiatives comprising the regional stimulus package are detailed in the following table.

Of the initiatives in delivery, it is estimated that this stimulus measure would sustain 40 to 50 full-time equivalent jobs, for a year.

Site Scope of Works Budget Current Status Proposed Finish
Clare Mechanical ventilation (air-conditioning) upgrade $550,000 Complete Complete
Penola Hydraulic services upgrade (warm water system) $50,000 Complete Complete
Cleve Hydraulic services upgrade (warm water system) $70,000 Complete Complete
Tanunda Back-up power capability upgrade (new back-up generator) $280,000 Complete Complete
Bordertown Electrical distribution network upgrade (switchboards and cabling) $200,000 Complete Complete
Barmera Communications (new site phone system) upgrade $110,000 Complete Complete
Kimba Structural remediation works $100,000 Complete Complete
Bordertown Site-wide nurse call system replacement $380,000 Complete Complete
Peterborough Electrical distribution network upgrade (switchboards and cabling) $355,000 Complete Complete
Eudunda Fire services compliance upgrade (fire sprinkler pipework) $480,000 Complete Complete
Gawler Back-up power capability upgrade (generator and switchboards) $850,000 Complete Complete
Renmark Fire water supply (new tanks) upgrade $260,000 Complete Complete
Murray Bridge Car park repair and resurfacing works $59,000 Complete Complete
Coober Pedy Electrical distribution network upgrade (switchboards and cabling) $598,000 Construction June 2021
Clare Electrical distribution network upgrade (switchboards and cabling) $550,000 Construction June 2021
Strathalbyn Back-up power capability upgrade (new back-up generator) $500,000 Construction June 2021
Naracoorte Central Sterile Services Department (CSSD) compliance upgrade $3,120,000 Construction June 2021
Naracoorte Hospital central hydraulic services upgrade (hot-water system) $400,000 Construction June 2021
Kapunda Fire services compliance upgrade (fire hydrant plant and sprinkler control) $300,000 Construction June 2021
Kingston Back-up power capability upgrade (new back-up generator) $250,000 Mobilisation June 2021
Loxton Fire services compliance upgrade (fire tanks, pumps and sprinklers) $1,800,000 Construction July 2021
Riverton Bathroom (resident ensuites) structural rectification works $150,000 Construction July 2021
Kapunda Central Sterile Services Department (CSSD) compliance upgrade $635,000 Construction July 2021
Waikerie Electrical distribution network upgrade (switchboards and cabling) $440,000 Mobilisation August 2021
Kangaroo Isl. Lift replacement (vertical transportation) $330,000 Manufacture August 2021
Angaston Central Sterile Services Department (CSSD) compliance upgrade $1,300,000 Tender Extended* October 2021
- Program Contingency & Staging Allowance $883,000 - -
Total Allocated $15,000,000