RAIL NETWORK UPGRADES
283 Dr McFETRIDGE (Morphett) (21 October 2008). What works will be undertaken as part of the $2.043 million allocated for 2008-09 as part of the upgrade/replacement of bridges on the Metropolitan Rail Network?
The Hon. P.F. CONLON (Elder—Minister for Transport, Minister for Infrastructure, Minister for Energy): I am advised as follows:
The $2.043 million will be used to upgrade the Port Adelaide Viaduct structure. Approximately $0.5 million was spent in 2008-09 with the remainder to be spent in 2009-10.