<!--The Official Report of Parliamentary Debates (Hansard) of the Legislative Council and the House of Assembly of the Parliament of South Australia are covered by parliamentary privilege. Republication by others is not afforded the same protection and may result in exposure to legal liability if the material is defamatory. You may copy and make use of excerpts of proceedings where (1) you attribute the Parliament as the source, (2) you assume the risk of liability if the manner of your use is defamatory, (3) you do not use the material for the purpose of advertising, satire or ridicule, or to misrepresent members of Parliament, and (4) your use of the extracts is fair, accurate and not misleading. Copyright in the Official Report of Parliamentary Debates is held by the Attorney-General of South Australia.-->
<hansard id="" tocId="" xml:lang="EN-AU" schemaVersion="1.0" xmlns:xlink="http://www.w3.org/1999/xlink" xmlns:xml="http://www.w3.org/XML/1998/namespace" xmlns:xsi="http://www.w3.org/2007/XMLSchema-instance" xmlns:mml="http://www.w3.org/1998/Math/MathML" xsi:noNamespaceSchemaLocation="hansard_1_0.xsd">
  <name>Legislative Council</name>
  <date date="2012-02-28" />
  <sessionName>Fifty-Second Parliament, Second Session (52-2)</sessionName>
  <parliamentNum>52</parliamentNum>
  <sessionNum>2</sessionNum>
  <parliamentName>Parliament of South Australia</parliamentName>
  <house>Legislative Council</house>
  <venue></venue>
  <reviewStage>published</reviewStage>
  <startPage num="223" />
  <endPage num="307" />
  <dateModified time="2022-08-06T14:30:00+00:00" />
  <proceeding continued="true">
    <name>Answers to Questions</name>
    <subject>
      <name>Desalination Plant</name>
      <text id="201202288ff34aa0084043b590000395">
        <heading>DESALINATION PLANT</heading>
      </text>
      <talker role="member" id="3404" kind="question">
        <name>The Hon. J.A. DARLEY</name>
        <house>Legislative Council</house>
        <questions>
          <question date="2012-02-28">
            <name>DESALINATION PLANT</name>
          </question>
        </questions>
        <text id="201202288ff34aa0084043b590000396">In reply to <by role="member" id="3404">the Hon. J.A. DARLEY</by> (19 October 2011) (First Session).</text>
      </talker>
      <talker role="member" id="3122" kind="answer">
        <name>The Hon. I.K. HUNTER</name>
        <house>Legislative Council</house>
        <electorate id="">Minister for Communities and Social Inclusion, Minister for Social Housing, Minister for Disabilities, Minister for Youth, Minister for Volunteers</electorate>
        <questions>
          <question date="2012-02-28">
            <name>DESALINATION PLANT</name>
          </question>
        </questions>
        <text id="201202288ff34aa0084043b590000397">
          <by role="member" id="3122">The Hon. I.K. HUNTER (Minister for Communities and Social Inclusion, Minister for Social Housing, Minister for Disabilities, Minister for Youth, Minister for Volunteers):</by>  The Minister for Water and the River Murray has been advised:</text>
        <text id="201202288ff34aa0084043b590000398">1.&amp;#x9;First water is the continuous and safe production of 10 per cent of the first 50 gigalitres desalination plant or approximately 15 million litres of desalinated drinking water per day. This was achieved in October 2011 and the desalination plant is currently supplying water into the SA Water network.</text>
        <text id="201202288ff34aa0084043b590000399">First drop of desalinated water is the commencement of production of desalinated water (Permeate). This was achieved in July 2011.</text>
        <text id="201202288ff34aa0084043b590000400">2.&amp;#x9;At the time of achieving the first drop of desalinated water, the contractor had produced in the order of 3.1 million litres of desalinated water (Permeate).</text>
        <text id="201202288ff34aa0084043b590000401">At the time of achieving first water in October 2011, the contractor demonstrated plant capacity of nearly 30 million litres per day.</text>
        <text id="201202288ff34aa0084043b590000402">3.&amp;#x9;As with all complex process plants, the contractor did encounter challenges associated with the electrical and protection trips on the high pressure pumps. These challenges were properly and methodically resolved.</text>