<!--The Official Report of Parliamentary Debates (Hansard) of the Legislative Council and the House of Assembly of the Parliament of South Australia are covered by parliamentary privilege. Republication by others is not afforded the same protection and may result in exposure to legal liability if the material is defamatory. You may copy and make use of excerpts of proceedings where (1) you attribute the Parliament as the source, (2) you assume the risk of liability if the manner of your use is defamatory, (3) you do not use the material for the purpose of advertising, satire or ridicule, or to misrepresent members of Parliament, and (4) your use of the extracts is fair, accurate and not misleading. Copyright in the Official Report of Parliamentary Debates is held by the Attorney-General of South Australia.-->
<hansard id="" tocId="" xml:lang="EN-AU" schemaVersion="4.0" xsi:noNamespaceSchemaLocation="hansard_1_0.xsd" xmlns:xlink="http://www.w3.org/1999/xlink" xmlns:xsi="http://www.w3.org/2007/XMLSchema-instance" xmlns:mml="http://www.w3.org/1998/Math/MathML">
  <name>House of Assembly</name>
  <date date="2024-05-02T11:00:00+09:30" />
  <sessionName>Fifty-Fifth Parliament, First Session (55-1)</sessionName>
  <parliamentNum>55</parliamentNum>
  <sessionNum>1</sessionNum>
  <parliamentName>Parliament of South Australia</parliamentName>
  <house>House of Assembly</house>
  <venue></venue>
  <reviewStage>published</reviewStage>
  <startPage num="7839" />
  <endPage num="7900" />
  <dateModified time="2024-07-26T15:08:17+09:30" />
  <proceeding continued="true">
    <name>Parliamentary Committees</name>
    <subject>
      <name>Public Works Committee: New Women's and Children's Hospital Early Works Package</name>
      <text id="20240502355908f6751f4a74a0000034">
        <heading>Public Works Committee: New Women's and Children's Hospital Early Works Package</heading>
      </text>
      <talker role="member" id="5387" referenceid="e05f224a87834b10abca5a0839ea45b3" kind="speech">
        <name>Mr BROWN</name>
        <house>House of Assembly</house>
        <electorate id="">Florey</electorate>
        <startTime time="2024-05-02T11:10:10+09:30" />
        <text id="20240502355908f6751f4a74a0000035">
          <timeStamp time="2024-05-02T11:10:10+09:30" />
          <by role="member" id="5387" referenceid="e05f224a87834b10abca5a0839ea45b3">Mr BROWN (Florey) (11:10):</by>  I move:</text>
        <text id="20240502355908f6751f4a74a0000036">
          <inserted>That the 62<sup>nd</sup> report of the committee, entitled New Women's and Children's Hospital Early Works Package, be noted.</inserted>
        </text>
        <text continued="true" id="20240502355908f6751f4a74a0000037">The Department for Health and Wellbeing (SA Health) proposes to commence an early works package for the new Women's and Children's Hospital on the Thebarton barracks site, which sits in close proximity to the Royal Adelaide Hospital and Adelaide BioMed City.</text>
        <text id="20240502355908f6751f4a74a0000038">In January 2023, the New Women's and Children's Hospital Act was proclaimed, which facilitated the development of the new hospital on the project site. Prior to construction, a range of enabling and supporting works are required, with a number of these works able to commence immediately to help the efficient use of project resources. These early works will maintain progress without materially impacting upon South Australia Police operations during their decommissioning and relocation process. The complete early works package includes:</text>
        <text id="20240502355908f6751f4a74a0000039">
          <item sublevel="1" bullet="true">relocation of engineering services from Gaol Road, Bonython Park works and temporary services;</item>
        </text>
        <text id="20240502355908f6751f4a74a0000040">
          <item sublevel="1" bullet="true">associated works for utility service relocations, including ongoing site investigations to determine existing conditions;</item>
        </text>
        <text id="20240502355908f6751f4a74a0000041">
          <item sublevel="1" bullet="true">stormwater outlet works;</item>
        </text>
        <text id="20240502355908f6751f4a74a0000042">
          <item sublevel="1" bullet="true">demolition and site clearing;</item>
        </text>
        <text id="20240502355908f6751f4a74a0000043">
          <item sublevel="1" bullet="true">construction of the hospital car park; and</item>
        </text>
        <text id="20240502355908f6751f4a74a0000044">
          <item sublevel="1" bullet="true">construction of a hospital central energy plant building.</item>
        </text>
        <text continued="true" id="20240502355908f6751f4a74a0000045">The ultimate aim of the early works package is to ensure that the necessary supporting infrastructure is in place to mitigate against project delays, to maintain the project program and to enable commencement of the main hospital later this year. The works will begin with the relocation of the authority services, delivery of stormwater infrastructure and improving site access along Bonython trail, which will allow for construction of the car park and central energy plant.</text>
        <text id="20240502355908f6751f4a74a0000046">SA Health states that, without implementation of this early works package, there is the possibility of cost escalation that is currently forecast at $10 million per month and prolongation of the entire project. Therefore, it is critical that the progress with these works is maintained to facilitate the main hospital works and to avoid unnecessary budget increases. Construction has commenced, with a major milestone of the works being the completion of the hospital car park, expected in early 2027. The capital cost is $306 million and forms part of the $3.2 billion new Women's and Children's Hospital project's approved budget.</text>
        <text id="20240502355908f6751f4a74a0000047">Construction of the hospital car park will improve site logistics for construction of the main hospital building by improving amenity and car parking for the trade workforce. The relationship between the car park and the central energy plant has been carefully considered to mitigate impact on the Parklands and Adelaide Gaol. The car park will be relocated closer to Port Road and the emergency department entry, with entry and logistic flows on the Port Road side of the development to ensure vehicles are kept away from the Parklands.</text>
        <page num="7842" />
        <text id="20240502355908f6751f4a74a0000048">Project management will follow best practice guidelines for project procurement and management, as advocated by the state government and construction industry authorities. This management will continue to incorporate development, consultation, evaluation and review over the lifespan of the project. To mitigate risks, a robust governance structure has been implemented which will be utilised at all stages of the project. This structure will ensure appropriate oversight through a single point of accountability, as well as effective project committees, decision-making activities, the separation of project governance and an organisational control structure.</text>
        <text id="20240502355908f6751f4a74a0000049">SA Health has incorporated ecologically sustainable principles into the scope of the works. The department states that facilities with good environmental qualities are essential to achieving a good value-for-money solution and will assist in creating a positive workplace, reducing energy and water consumption, reducing the consumption of renewable and non-renewable resources, and minimising recurrent costs associated with the project.</text>
        <text id="20240502355908f6751f4a74a0000050">The project will incorporate key design principles to reduce energy and water use and associated greenhouse gas emissions. This will include installing a solar system on the new car park roof to supplement the hospital's electrical demand, natural ventilation and stormwater treatment to meet Green Star criteria and other legislated requirements.</text>
        <text id="20240502355908f6751f4a74a0000051">The Central Archive has identified two Aboriginal cultural sites near the proposed works location. Authorisation has been sought and received from the Minister for Aboriginal Affairs and Reconciliation, and a cultural heritage management plan will be utilised and negotiated with traditional owners. Due to the location and nature of the site, there is potential for heritage artifacts, works or evidence of past occupation and use of the site being uncovered during ground-disturbing activities. As a result, the project has engaged a qualified archaeologist to provide advice and manage any discoveries made during the construction process. SA Health states that native title has been extinguished over the whole site area.</text>
        <text id="20240502355908f6751f4a74a0000052">The department affirms that consultation and engagement with the Women's and Children's Health Network clinicians, staff, consumers and stakeholders have occurred to finalise the new hospital's concept design. Relevant stakeholders and precinct partners have also been extensively consulted throughout the development of the new hospital to ensure that opportunities to open and rejuvenate the surrounding Parklands are incorporated into the project. The project team regularly engages with Kaurna representatives, which will be ongoing to include assisting in the development of the interior narrative of the new hospital's design.</text>
        <text id="20240502355908f6751f4a74a0000053">The committee examined written and oral evidence in relation to the new Women's and Children's Hospital early works project. Witnesses who appeared before the committee were:</text>
        <text id="20240502355908f6751f4a74a0000054">
          <item sublevel="1" bullet="true">Dr Robyn Lawrence, Chief Executive, Department of Health and Wellbeing;</item>
        </text>
        <text id="20240502355908f6751f4a74a0000055">
          <item sublevel="1" bullet="true">Brendan Hewitt, Project Director, New Women's and Children's Hospital Project, Department of Health and Wellbeing;</item>
        </text>
        <text id="20240502355908f6751f4a74a0000056">
          <item sublevel="1" bullet="true">Daniel Shaw, Construction Manager, Lendlease Building Contractors; and</item>
        </text>
        <text id="20240502355908f6751f4a74a0000057">
          <item sublevel="1" bullet="true">Thomas Masullo, Director, Woods Bagot.</item>
        </text>
        <text continued="true" id="20240502355908f6751f4a74a0000058">I thank the witnesses for their time.</text>
        <text id="20240502355908f6751f4a74a0000059">Based upon the evidence considered and pursuant to section 12C of the Parliamentary Committees Act 1991, the Public Works Committee reports to parliament that it recommends the proposed public work.</text>
        <text id="20240502355908f6751f4a74a0000060">Motion carried.</text>
      </talker>
    </subject>
  </proceeding>