<!--The Official Report of Parliamentary Debates (Hansard) of the Legislative Council and the House of Assembly of the Parliament of South Australia are covered by parliamentary privilege. Republication by others is not afforded the same protection and may result in exposure to legal liability if the material is defamatory. You may copy and make use of excerpts of proceedings where (1) you attribute the Parliament as the source, (2) you assume the risk of liability if the manner of your use is defamatory, (3) you do not use the material for the purpose of advertising, satire or ridicule, or to misrepresent members of Parliament, and (4) your use of the extracts is fair, accurate and not misleading. Copyright in the Official Report of Parliamentary Debates is held by the Attorney-General of South Australia.-->
<hansard id="" tocId="" xml:lang="EN-AU" schemaVersion="4.0" xmlns:xlink="http://www.w3.org/1999/xlink" xmlns:xml="http://www.w3.org/XML/1998/namespace" xmlns:xsi="http://www.w3.org/2007/XMLSchema-instance" xmlns:mml="http://www.w3.org/1998/Math/MathML" xsi:noNamespaceSchemaLocation="hansard_1_0.xsd">
  <name>Estimates Committee A - Answers to Questions</name>
  <date date="2013-11-15T00:00:00+10:30" />
  <sessionName>Fifty-Second Parliament, Second Session (52-2)</sessionName>
  <parliamentNum>52</parliamentNum>
  <sessionNum>2</sessionNum>
  <parliamentName>Parliament of South Australia</parliamentName>
  <house>Estimates Committee A - Answers to Questions</house>
  <venue></venue>
  <reviewStage>published</reviewStage>
  <startPage num="17" />
  <endPage num="60" />
  <dateModified time="2023-06-16T13:37:10+09:30" />
  <proceeding continued="true">
    <name>Estimates Replies</name>
    <subject>
      <name>Motor Accident Commission</name>
      <text id="20131115c05df3b138ed4646a0000227">
        <heading>MOTOR ACCIDENT COMMISSION</heading>
      </text>
      <talker role="member" id="1804" kind="question">
        <name>In reply to Ms CHAPMAN</name>
        <house>House of Assembly</house>
        <electorate id="">Bragg</electorate>
        <portfolios>
          <portfolio id="">
            <name>Deputy Leader of the Opposition</name>
          </portfolio>
        </portfolios>
        <questions>
          <question date="2013-11-15">
            <name>MOTOR ACCIDENT COMMISSION</name>
          </question>
        </questions>
        <text id="20131115c05df3b138ed4646a0000228">In reply to <by role="member" id="1804">Ms CHAPMAN (Bragg—Deputy Leader of the Opposition)</by> (28 June 2013).</text>
      </talker>
      <talker role="member" id="1808" kind="answer">
        <name>The Hon. M.F. O'BRIEN</name>
        <house>House of Assembly</house>
        <electorate id="">Napier</electorate>
        <portfolios>
          <portfolio id="">
            <name>Minister for Finance</name>
          </portfolio>
          <portfolio id="">
            <name>Minister for Police</name>
          </portfolio>
          <portfolio id="">
            <name>Minister for Correctional Services</name>
          </portfolio>
          <portfolio id="">
            <name>Minister for Emergency Services</name>
          </portfolio>
          <portfolio id="">
            <name>Minister for Road Safety</name>
          </portfolio>
        </portfolios>
        <questions>
          <question date="2013-11-15">
            <name>MOTOR ACCIDENT COMMISSION</name>
          </question>
        </questions>
        <text id="20131115c05df3b138ed4646a0000229">
          <by role="member" id="1808">The Hon. M.F. O'BRIEN (Napier—Minister for Finance, Minister for Police, Minister for Correctional Services, Minister for Emergency Services, Minister for Road Safety):</by>  South Australia's Road Safety Strategy 2020 recognises that, while new road construction and road safety projects are expensive, there are considerable benefits to be gained when these projects are well planned, designed and managed. Research shows that investment in road safety projects can produce crash savings with a value at least 10 times the cost of the infrastructure.</text>
        <text id="20131115c05df3b138ed4646a0000230">A $52.4 million Motor Accident Commission (MAC) funding for a series of projects was announced under the 2013-14 state budget. These projects are expected to reduce the number and severity of crashes as detailed below.</text>
        <text id="20131115c05df3b138ed4646a0000231">1.&amp;#x9;Britannia Roundabout Upgrade—</text>
        <text id="20131115c05df3b138ed4646a0000232">
          <item sublevel="2" bullet="true">Project involves redesigning the existing five-leg roundabout into two smaller roundabouts (one with three legs and one with four legs).</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000233">
          <item sublevel="2" bullet="true">Capital cost of $3.2 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000234">
          <item sublevel="2" bullet="true">Assessed over an appraisal period of 20 years and using a discount rate of 6 per cent.</item>
        </text>
        <page num="51" />
        <text id="20131115c05df3b138ed4646a0000235">
          <item sublevel="2" bullet="true">Expected present value traffic delay savings of $14.0 million, vehicle operating cost savings of $1.0 million, and crash savings of $9.0 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000236">
          <item sublevel="2" bullet="true">Resultant total present value benefit of $24.37 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000237">
          <item sublevel="2" bullet="true">Benefit cost ratio of 8.07.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000238">
          <item sublevel="2" bullet="true">Total crashes expected to be reduced by 33 per cent (based on crash history during the five years from 2007-11).</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000239">2.&amp;#x9;North East Road/Sudholz Road Intersection Upgrade—</text>
        <text id="20131115c05df3b138ed4646a0000240">
          <item sublevel="2" bullet="true">Project involves removing right-turn movements from North East Road and fully controlling right turns from Sudholz Road. Right-turn vehicles from North East Road will be diverted to a new signalised intersection at Sudholz Road/Blacks Road.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000241">
          <item sublevel="2" bullet="true">Capital cost of $7.7 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000242">
          <item sublevel="2" bullet="true">Assessed over an appraisal period of 30 years and using a discount rate of 6 per cent.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000243">
          <item sublevel="2" bullet="true">Expected present value traffic delay savings of $22.5 million and crash savings of $4.9 million. An increase of $0.1 million in vehicle operating costs is also expected.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000244">
          <item sublevel="2" bullet="true">Resultant total present value benefit of $27.3 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000245">
          <item sublevel="2" bullet="true">Benefit cost ratio of 3.97.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000246">
          <item sublevel="2" bullet="true">Total crashes expected to be reduced by 41 per cent (based on crash history during the four years from 2008-11).</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000247">3.&amp;#x9;Magill Road/Glynburn Road Intersection Upgrade—</text>
        <text id="20131115c05df3b138ed4646a0000248">
          <item sublevel="2" bullet="true">Project involves separate right-turn lanes on Magill Road and Glynburn Road, a short left-turn lane on Magill Road into Glynburn Road, new traffic signals and upgraded road lighting.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000249">
          <item sublevel="2" bullet="true">Capital cost of $4.0 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000250">
          <item sublevel="2" bullet="true">Assessed over an appraisal period of 30 years and using a discount rate of 6 per cent.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000251">
          <item sublevel="2" bullet="true">Expected present value traffic delay savings of $19.0 million, vehicle operating cost savings of $5.0 million, and crash savings of $2.0 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000252">
          <item sublevel="2" bullet="true">Resultant total present value benefit of $26.0 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000253">
          <item sublevel="2" bullet="true">Benefit cost ratio of 6.45.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000254">
          <item sublevel="2" bullet="true">Casualty crashes expected to be reduced by 68 per cent (based on crash history during the five years from 2008-12).</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000255">4.&amp;#x9;Golden Grove Road/Grenfell Road (East) Intersection Upgrade—</text>
        <text id="20131115c05df3b138ed4646a0000256">
          <item sublevel="2" bullet="true">Project involves the installation of new traffic signals at the existing unsignalised intersection.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000257">
          <item sublevel="2" bullet="true">The intersection of Golden Grove Road/Grenfell Road (West) which is located only 140 metres away is already signalised.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000258">
          <item sublevel="2" bullet="true">Capital cost of $2.5 million.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000259">
          <item sublevel="2" bullet="true">This project is proactive in nature and aims to address existing safety concerns at the intersection.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000260">
          <item sublevel="2" bullet="true">These safety concerns are the high speed at which turning movements can be performed and the weaving movement of vehicles turning left from Grenfell Road (East) onto Golden Grove Road and then turning right into Grenfell Road (West).</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000261">
          <item sublevel="2" bullet="true">Project was identified as a priority in the draft Road Management Plan (RMP) for Golden Grove Road developed by the Department for Planning, Transport and Infrastructure's metropolitan region.</item>
        </text>
        <page num="52" />
        <text id="20131115c05df3b138ed4646a0000262">
          <item sublevel="2" bullet="true">The installation of traffic signals at this location has been the subject of various requests from the public.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000263">5.&amp;#x9;APY Lands Main Access Road Upgrade—</text>
        <text id="20131115c05df3b138ed4646a0000264">
          <item sublevel="2" bullet="true">Cost of $21.0 million (state government contribution to overall project cost of $106.0 million).</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000265">
          <item sublevel="2" bullet="true">Federal government will contribute funding under Nation Building 2 program. Note that this funding will only commence from 2014-15.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000266">
          <item sublevel="2" bullet="true">Project was assessed using a multi-criteria approach used for infrastructure proposals for remote Indigenous communities, rather than a cost-benefit analysis.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000267">
          <item sublevel="2" bullet="true">The multi-criteria approach used follows the method outlined in the draft National Policy Framework on Infrastructure in Remote Indigenous Communities developed by Infrastructure Australia.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000268">
          <item sublevel="2" bullet="true">Note that the National Policy Framework is a draft document and has not been released to the public</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000269">6.&amp;#x9;South Eastern Freeway Upgrade—</text>
        <text id="20131115c05df3b138ed4646a0000270">
          <item sublevel="2" bullet="true">Cost of $12.5 million (state government contribution to overall project cost of $25.0 million)</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000271">
          <item sublevel="2" bullet="true">Federal government will contribute funding under Nation Building 2 program. Note that this funding will only commence from 2014-15.</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000272">
          <item sublevel="2" bullet="true">Consists of two components:</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000273">
          <item sublevel="2" bullet="true">Advanced traffic management system between Stirling and Mount Barker (benefit cost ratio of 1.3);</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000274">
          <item sublevel="2" bullet="true">Managed motorway system between Crafers and Stirling (benefit cost ratio of 2.2).</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000275">7.&amp;#x9;Additional road safety cameras on metropolitan roads—</text>
        <text id="20131115c05df3b138ed4646a0000276">
          <item sublevel="2" bullet="true">Cost of $1.5 million (for 10 sites)</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000277">
          <item sublevel="2" bullet="true">Benefit cost ratio of 14.6 is based only on pedestrian injury reduction saving for 2013-14 (at a cost of $1.50 million for 10 sites)</item>
        </text>
        <text id="20131115c05df3b138ed4646a0000278">
          <item sublevel="2" bullet="true">The average installation cost per site is generally constant across the network with the expected pedestrian safety benefits also generally constant.</item>
        </text>